Ongoing construction work for Horizon 120 and road or path closures

Residents will be aware that work is ongoing to construct the Horizon 120 business park on the far side of the A131.

It is necessary for the contractors to close certain roads and footpaths from time to time particularly to enable them to connect the development on to service media such as gas and water and this page is to assist you with information about the road and path closures as well as the schedule of closures shown further down on this page.

Find out about the closure of Cuckoo Way

Find out about the closure of part of footpath 26

The schedule of works are as follows

A131, Garden Village Way Roundabout (gas & water) - start date 8 March 2021 to 2 April 2021

Cuckoo Way (gas & water) - start date 8 March 2021 to 2 April 2021

Footpath part 1 (gas) - start date 22 March 2021 to 9 April 2021

Notley Green Roundabout (gas) - start date 5 April 2021 to 16 April 2021

Footpath Part 2 (gas) - start date 29 March 2021 to 30 April 2021

 

  1. London Road (gas POC) - start date 26/4/21 - 10/5/21